Cheniere’s Corpus Christi LNG expansion project 66 percent complete

Energy News Beat

Cheniere’s Corpus Christi liquefaction plant now has three operational trains, each with a capacity of about 5 mtpa.

In June 2022, Cheniere made the final investment decision on the Corpus Christi Stage 3 expansion project, worth about $8 billion. Compatriot Bechtel officially started construction on the project in October of the same year.

The project includes building seven midscale trains, each with an expected liquefaction capacity of about 1.49 mtpa.

Cheniere’s unit, Corpus Christi Liquefaction, said in the August construction report filed with the US FERC on Monday that the overall project completion rate for Stage 3 is 65.9 percent.

The project was 64 percent complete as of the end of July.

Stage 3 engineering and procurement are 95.1 percent and 82.5 percent complete, respectively, while subcontract and direct hire construction work are 86.7 percent and 30.3 percent complete, respectively.

During August, key work fronts included aboveground piping in train 1 and outside boundary limits (OSBL), concrete pours in trains 2 – 6 and structural steel erection in trains 2 – 4 and OSBL, underground piping installation in trains 4 – 7 and OSBL, and equipment setting in trains 1 – 6.

Additional continued work includes road improvements, drainage work, and mobilization of temporary facilities, equipment, and personnel, CCL said.

Moreover, Bechtel continued testing and installing aboveground piping and pipe spools on train 1.

During August, Bechtel will continue this work at the first train and also start loop checks for mixed refrigerant compressors.

CCL Stage 3 (Image: Cheniere)

Cheniere initially said that LNG deliveries from the expansion project were expected to begin in 2025 with full production in 2027.

However, Cheniere’s CEO Jack Fusco said in August last year that the company is expecting to complete the expansion phase ahead of schedule.

The company confirmed in its second quarter report that it expects to achieve first LNG production from the first train at the end of 2024.

Also, the company said it expects first gas into the first train 1 in about 2 months.

Substantial completion of the project is expected during 1H 2025 – 2H 2026.

In addition to this expansion, Cheniere plans to build two more liquefaction trains as part of the third expansion phase at the Corpus Christi plant.

Cheniere aims to to take a final investment decision on this project in 2025.

Also, Cheniere aims to build two new liquefaction trains as part of the Sabine Pass Stage 5 expansion project to add up to 20 mtpa of capacity to the giant 30 mtpa facility.

Source: Lngprime.com

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post Cheniere’s Corpus Christi LNG expansion project 66 percent complete appeared first on Energy News Beat.

 

TotalEnergies, HD Hyundai Chemical ink LNG supply deal

Energy News Beat

Under the deal, TotalEnergies will deliver 200,000 tons of LNG per year for seven years starting from 2027.

Thanks to this agreement, with prices indexed both to Brent and Henry Hub, TotalEnergies strengthens its long-term position in South Korea, the world’s third-largest LNG importing country, TotalEnergies said in a statement.

Gregory Joffroy, senior VP of LNG at TotalEnergies, said this deal will ensure natural gas supplies to one of HD Hyundai Chemical’s industrial sites.

“This agreement allows us to continue securing long-term sales in Asia and reduce our exposure to spot market gas prices,” he said.

In line with its strategy to grow its long-term LNG sales, TotalEnergies and China’s CNOOC recently agreed to extend their existing long-term LNG supply and purchase deal.

The company announced a five-year extension of its SPA with CNOOC, for the delivery of 1.25 million tons of LNG per year to China until 2034.

Before this, TotalEnergies entered into a heads of agreement with Türkiye’s state-owned natural gas and LNG firm Botas.

Under this 10-year contract, Botas will receive 16 LNG cargoes or up to 1.6 billion cubic meters per year from TotalEnergies.

In addition, TotalEnergies entered into deals to supply LNG to Indian Oil and Korea South-East Power.

TotalEnergies says it is the world’s third largest LNG player with a global portfolio of 44 Mt/y in 2023 thanks to its interests in liquefaction plants in all geographies.

The company benefits from an integrated position across the LNG value chain, including production, transportation, access to more than 20 Mt/y of regasification capacity in Europe, trading, and LNG bunkering.

TotalEnergies’ ambition is to increase the share of natural gas in its sales mix to close to 50 percent by 2030.

Source: Lngprime.com

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post TotalEnergies, HD Hyundai Chemical ink LNG supply deal appeared first on Energy News Beat.

 

Another African nation interested in joining BRICS

Energy News Beat

 

Membership presents an opportunity to challenge the dominance of the dollar and euro, the Burkinabe prime minister says

Prime Minister of Burkina Faso Apollinaire Joachim Kyelem de Tambela has expressed an interest in joining BRICS.

Membership of the group would make it possible to challenge the “domination of the dollar and the euro,” and to achieve “fairer trade relations on the international stage,” he said at a meeting with Russian Ambassador Igor Martynov in Ouagadougou on Monday.

Following the meeting, the government of the West African republic published a post on Facebook, confirming that Kyelem de Tambela had “argued for Burkina Faso’s joining the integration of BRICS countries (Brazil, Russia, India, China and South Africa).”

Martynov discussed proposals for Russia to develop a nuclear power plant in Burkina Faso. “The meeting was very fruitful and successful. We are in tune regarding our approaches to bilateral cooperation. We also dwelled on intensifying our cooperation in all areas,” he said.

In June 2023, the Burkinabe government and the BRICS group signed a memorandum of understanding for cooperation. The document defines areas of cooperation, which include the economy, health, education, infrastructure, air and rail transport, industry, commerce, mines, energy, sport, culture, information and communication technologies, and tourism.

BRICS was founded in 2006 by Brazil, Russia, India, and China, with South Africa joining in 2011. The group expanded this year when Egypt, Ethiopia, Iran, and the United Arab Emirates became full members.

On September 2, Bloomberg reported, citing sources, that Türkiye had officially applied to join BRICS, citing “the need for cooperation with developing countries.”

In June, the Zimbabwean Defense Minister Oppah Muchinguri-Kashiri announced that the country was ready to join the BRICS group of nations.

Several other countries have also officially signaled their intention to join the organization. Russian Deputy Foreign Minister Sergey Ryabkov has said that one of the key criteria for Moscow to welcome new members is that any country seeking to join BRICS refrains from participating in illegal unilateral sanctions.

Source: Rt.com

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post Another African nation interested in joining BRICS appeared first on Energy News Beat.

 

Infrastructure Bill’s Big-Budget Projects A ‘Complete Failure’ Despite Billions Spent

Energy News Beat

The infrastructure bill, once hailed as a game-changer, has flopped—rural broadband and EV stations are stuck in the slow lane, leaving critics fuming.

Democrats have touted the infrastructure bill Congress passed in 2021 as a signature accomplishment of the Biden-Harris administration, but some of its ambitious projects have fallen far short of expectations nearly three years after President Joe Biden signed it into law. [emphasis, links added]

A massive program to expand rural broadband access has failed so far to connect any homes to the Internet. A push to electrify school bus fleets has proved costly and inefficient.

And a multibillion-dollar effort to build thousands of electric vehicle charging stations across the country has so far yielded just a handful of stations.

The Infrastructure Investment and Jobs Act contained $1.2 trillion in spending on what the White House called “a once-in-a-generation investment in our nation’s infrastructure and competitiveness.”

But critics say the progressive goals of the Biden-Harris administration held back the law from delivering sweeping updates to the nation’s infrastructure.

“I was very skeptical that it would actually deliver those kinds of results,” David Ditch, senior policy analyst at the Heritage Foundation, told the Washington Examiner. “It has dramatically underperformed even my low expectations, and there’s a lot of reasons for that.”

“No. 1 is the Biden administration has been absolutely determined to apply as many different left-wing mandates as it can cram in,” Ditch added.

From “environmental justice” considerations to equity requirements for contractors, many programs created by the infrastructure bill came with progressive stipulations for how they should be implemented.

The result has been slow progress in spending enormous sums of money, with little to show for some efforts after nearly three years.

“The evidence of these programs being a complete failure is that none of the recipients, grantees, have featured in a [Kamala] Harris commercial or onstage,” Daniel Turner, executive director at Power the Future, told the Washington Examiner.

“If you received a benefit from the infrastructure bill or the Inflation Reduction Act, you would be front and center saying, ‘Thank you, madame vice president, for this program.’”

Instead, the infrastructure bill has made few appearances in Harris’s campaign rhetoric as she seeks to distance herself from Biden.

Read rest at Examiner

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post Infrastructure Bill’s Big-Budget Projects A ‘Complete Failure’ Despite Billions Spent appeared first on Energy News Beat.

 

As Demand Drops, Automakers Reverse EV Targets Despite Billions In Biden-Harris Subsidies

Energy News Beat

Automakers are backpedaling on EV targets as consumer demand wanes, despite billions in Biden-Harris subsidies and a push for charging stations.

Automakers have continued to backpedal on electric vehicle (EV) targets over the last year as a slackening of consumer demand has hampered growth despite the billions in subsidies lavished on the industry by the Biden-Harris administration. [emphasis, links added]

A wide array of auto manufacturers have abandoned key EV goals since February, with Volvo, Ford, and Mercedes-Benz all dialing back electric quotas or dropping previously planned product lines.

The shifts in corporate strategy suggest the EV transition — once touted by auto executives like Ford CEO Jim Farley as the industry’s future — may not be as feasible as once thought due to consumer aversion to lower mileage ranges, a lack of charging infrastructure, and higher prices, experts told the Daily Caller News Foundation.

The auto industry’s change in direction is despite the billions in subsidies doled out to the industry via the 2021 Bipartisan Infrastructure Bill and the 2022 Inflation Reduction Act, with the White House offering a $7,500 federal tax credit for certain EVs to ease costs for buyers, and allocating $12 billion for carmakers to retrofit factories for EV production.

The administration has also put in place stringent regulations designed to phase out internal combustion engine vehicles, including a tailpipe emissions rule that would effectively require about 67% of all light-duty vehicles sold after model year 2032 to be electric vehicles (EVs) or hybrids.

“Even after throwing money at EVs hand over fist, basically paying people tax dollars to drive these cars off the lots, you have a dire spiral of (1) not enough demand to support the number of cars being produced, and (2) the people you paid to buy them now wanting to go back to what they had before,” O.H. Skinner, executive director of the Alliance for Consumers and the former solicitor general of Arizona, told the DCNF.

Despite the generous tax credits, consumers have been hesitant to adopt EVs at the rate the Biden-Harris administration and automakers had hoped, with EV sales growing 50% in the first half of 2023 and 31% in the first half of 2024, less than the 71% increase in the first half of 2022.

Moreover, a June poll from The Associated Press-NORC Center for Public Affairs Research and the University of Chicago’s Energy Policy Institute found that 46% of respondents were unlikely or very unlikely to purchase an EV, while just 21% were “very” or “extremely” likely to make the change.

Consumer sentiment towards EVs has struggled even among those who have already purchased the vehicles, with a June survey from leading consulting firm McKinsey and Company finding nearly half of Americans who own an EV want to go back to a standard vehicle.

“The [EV market] headwinds come from physical realities that translate into economic and practical realities,” Mark Mills, a distinguished senior fellow at the Texas Public Policy Foundation and an expert on the automobile market, told the DCNF.

“EVs are inherently more expensive… and most consumers are very price sensitive; EV fueling for most people is far less convenient… [and] EV fueling infrastructure is extremely expensive and will take a long time to build out.”

The average cost of a new EV was 10% higher than the price of a standard vehicle as of January, with the 2024 electric version of a base Ford F-150 costing roughly $20,000 more. The Ford F-Series was the best-selling vehicle in the U.S. in 2023.

Ford canceled plans to produce a three-row electric SUV in August and reduced output of its F-150 Lightning pickup truck in January.

The reversals follow Ford’s loss of $4.7 billion on EVs in 2023, equating to nearly $65,000 per EV it sold. When reached, a Ford spokeswoman referred back previous comments to the DCNF, stating that “we aren’t going to launch vehicles unless they are going to be profitable within 12 months of launch.”

Beyond a lack of infrastructure, charging can simply be inconvenient for consumers, with refueling times ranging from 20 minutes to upwards of 50 hours…

“These are staggering costs to impose on American families,” Diana Furchtgott-Roth, director of the Center for Energy, Climate and Environment at the Heritage Foundation, told the DCNF.

EV carmakers Tesla and Lucid have also struggled in the last year, announcing plans to lay off roughly 10% and 6% of their workforces, respectively.

On top of sheer cost, expanding charging infrastructure has also been a challenge for manufacturers, with the Biden-Harris administration having built just [eight] EV charging stations in four states as of April 2024, despite the Bipartisan Infrastructure Bill earmarking $7.5 billion for the creation of a national EV charger network.

A lack of demand, union requirements, as well as diversity, equity, and inclusion initiatives, with the Department of Transportation requiring applicants to promise to perform “intentional outreach to underserved communities” by hosting “neighborhood block parties” to qualify for funding, have significantly slowed down the project’s rollout.

Beyond a lack of infrastructure, charging can simply be inconvenient for consumers, with refueling times ranging from 20 minutes to upwards of 50 hours depending on charger voltage and battery size, according to American automotive resource company Edmunds.

Even “fast charging” in the urban center of Washington, D.C., can take as long as 35 minutes.

Faced with these obstacles, Volvo Cars abandoned plans to offer an all-electric line-up by the end of the decade, instead aiming to have between 90% and 100% of its cars be fully electric or plug-in hybrids by that time.

Mercedes-Benz made a similar announcement back in February, slashing its target of selling 100% EVs by 2030 to just 50% after its net profit fell 21.5% year-over-year in the fourth quarter of 2023.

Read rest at Daily Caller

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post As Demand Drops, Automakers Reverse EV Targets Despite Billions In Biden-Harris Subsidies appeared first on Energy News Beat.

 

California’s backlogged grid is holding up its electric truck dreams

Energy News Beat

 

Across California, the companies that are trying to build charging stations for electric trucks are being told that it will take years — or even up to a decade — for them to get the electricity they need. That’s because utilities are failing to build out the grid fast enough to meet that demand.

This poses a major problem for a state that’s aiming to clean up its trucking industry. California has the most aggressive set of truck electrification goals in the country, and compliance deadlines are coming up fast.

State legislators did pass two laws last year — SB 410 and AB 50 — ordering regulators to find ways to speed up the process of getting utility customers the grid power they need, and last week the California Public Utilities Commission issued a decision meant to set timeframes for this work.

But charging companies, electric truck manufacturers, and environmental advocates are not happy with the result. They say the decision does next to nothing to get utilities to move faster or work harder to serve the massive charging hubs being planned across the state.

“It’s shocking how little the commission did here. They basically adopted status quo timelines across the board,” said Sky Stanfield, an attorney working with the Interstate Renewable Energy Council, a nonprofit clean energy advocacy group.

California’s struggle to deal with this issue is raising doubts about not only whether the state can meet its own climate goals but also whether truck electrification targets are achievable at all. States in the U.S. Northeast and Pacific Northwest with transportation-electrification targets will also need to build megawatt-scale charging along highways. Those projects will likewise require grid capacity upgrades that take a much longer time to plan and build than charging sites for passenger vehicles.

Stanfield and IREC believe that the CPUC’s decision both is inadequate and runs counter to clear instruction from California law. SB 410 orders the CPUC to craft regulations that ​“improve the speed at which energization and service upgrades are performed” and push the state’s big utilities to upgrade their grids ​“in time to achieve the state’s decarbonization goals.”

But the state’s electric truck targets simply won’t be met if charging stations aren’t built more rapidly, Stanfield said. ​“No one’s going to buy a fancy EV truck that costs well over $100,000 if they can’t charge it.”

IREC isn’t alone in this perspective. Powering America’s Commercial Transportation, a consortium of major EV charging and manufacturing companies, wrote in its comments to the CPUC that the decision ​“does not comply with either the requirements or legislative intent” of the law.

PACT asked the CPUC to set a two-year maximum timeline for utilities to build new substations and complete the more complex grid upgrades required by large EV charging depots.

But instead, the CPUC simply had Pacific Gas and Electric, Southern California Edison , and San Diego Gas & Electric report how long these major ​“upstream capacity” grid projects are taking today and then used the lower average of that historical data to set maximum timelines that utilities should meet in the future.

Those timelines are much, much too long, electric truck manufacturers, charging-project developers, and clean transportation advocates say. They stretch from nearly two years for upgrading distribution circuits and nearly three years for upgrading substations to nearly nine years for building the new substations that utilities say they’ll need to power truck-charging depots currently being built.

(California Public Utilities Commission)

“We’ve put in millions of dollars in the facilities we’ve already upgraded, and more that are in motion,” said Paul Rosa, a PACT board member.

As senior vice president of procurement and fleet planning at truck leasing company Penske, he is responsible for the company’s transport projects, including truck-charging projects in Southern and Central California.

But those projects represent just a fraction of the 114,500 chargers required to support the 157,000 medium- and heavy-duty vehicles that the California Energy Commission forecasts the state will need by 2030.

“If we can’t get the power, this all comes to a screeching halt,” Rosa said.

The slow and burdensome process of getting new customers connected to the grid — ​“energization” in CPUC parlance — isn’t a problem for just EV trucks.

PG&E has been under fire for years for failing to deliver timely grid hookups to everyday commercial and residential projects — a result, critics say, of poor planning and resource management.

The CPUC’s new decision does set a 125-business-day maximum timeline for these less complicated energizations. If those targets are met by utilities, ​“maximum timelines for grid connections could be reduced up to 49 percent compared to current operations,” the CPUC noted in a fact sheet accompanying the decision.

“I think the commission got it right” on these less complicated energization targets, said Tom Ashley, vice president of government and utility relations at Voltera, a company building EV charging projects across the state.

But how the commission handled the larger-scale grid upgrades — the kind needed to get EV truck-charging stations up and running — is a different story, he said. ​“That is where the industry is really frustrated that we didn’t get the help, and the utilities didn’t get the direction.”

The state’s Advanced Clean Trucks rule requires truck manufacturers to hit minimum targets for zero-emissions trucks as a percentage of total sales over the coming years, ratcheting from 30% of all medium- and heavy-duty vehicles by 2028 to 50% by 2030.

And California’s Advanced Clean Fleets rule requires the state’s biggest trucking and freight companies to convert hundreds of thousands of diesel trucks to zero-emissions models over the next 12 years, with earlier targets for certain classes of vehicles, including the heavy trucks carrying cargo containers from California’s busy and polluted ports.

Right now, many of the plans to build charging hubs for those trucks are stuck in grid-upgrade limbo — and the CPUC decision offers little indication it will get them unstuck.

“We’ve submitted for well over 50 projects in the past two years, looking for the right property to acquire,” said Jason Berry, director of energy and utilities at Terawatt Infrastructure. The startup has more than $1 billion in equity and project finance lined up to build large-scale charging hubs, including a network that will stretch from California to Texas along the I-10 highway, a major trucking corridor.

But of the sites Terawatt has scouted in California, ​“about 95% of those do not have the power we’re trying to request,” Berry said. To serve proposed charging hubs in California’s Inland Empire, utility SCE has said that it will need to expand existing substations, which takes four to five years, or build a new substation, which takes at least eight years, Terawatt said in May comments to the CPUC.

Terawatt is far from the only company facing delays. In testimony to the CPUC, Berry pointed out that Tesla has told the agency that 12 Supercharger sites with 522 charging stalls are facing delays because of capacity issues in SCE territory. A state-funded electric truck-charging project in the Inland Empire is also held up due to similar constraints.

The main problem is that large-scale charging sites can be built much faster than utilities are used to moving, Berry said. ​“We’re building projects, maybe ideally starting at 10 megawatts and then going to 20 megawatts,” Berry said. That’s about the same load on the grid as would be caused by an entirely new residential neighborhood or big commercial or industrial site.

But while those sites typically take years to plan and build, a new truck-charging site can go from planning to completion in less than a year.

“They have to have a mechanism to start on those things, or every single project is going to be four to five years out — which is what we’re being told on so many of these today,” he said.

The same point was made by Diego Quevedo, utilities lead and senior charging-infrastructure engineer at Daimler Truck North America, which joined fellow electric truck manufacturers Volvo Group North America and Navistar to weigh in on the CPUC proceeding.

“Trucks can be manufactured by OEMs and delivered approximately six months after receiving an order,” Quevedo said in testimony before the CPUC. But fleets won’t order trucks if they lack the confidence the utility grid infrastructure will be built and energized when the trucks are delivered.”

Utilities’ grid-capacity additions are taking from seven to 10 years to ​“plan, design, budget, construct, and energize,” he said. Unless those capacity expansions can be sped up significantly, ​“electric trucks become expensive stranded assets that are unable to charge,” he said.

California’s major utilities have a different perspective. They’ve argued in comments to the CPUC that it may be difficult or impossible to move more quickly on such complicated work.

First, as utilities have pointed out, many of the things that can slow down major grid projects are beyond their control. In a filing with the CPUC, PG&E noted that ​“one capacity upgrade project may face an extended timeline due to lengthy environmental assessments and permitting processes, and another may encounter challenges in acquiring materials in a timely manner due to manufacturer issues.”

IREC’s Stanfield conceded that equipment backlogs and environmental and permitting reviews are barriers to moving more quickly. ​“But we have to make it go faster if we want to hit our climate goals, if we want manufacturers to build clean trucks.”

And there’s an even bigger challenge to making major changes to the grid in anticipation of booming demand from EV charging: the cost involved.

“Lack of funding is the big block to meet the anticipated load growth,” Terawatt’s Berry said.

California’s utilities are already spending more than they ever have on their power grids, for myriad reasons. They are passing the costs of grid-hardening investments and integrating new clean energy into the power system on to customers in the form of electricity rates that are now the highest in the continental U.S.

Electricity rate increases are an economic and political crisis in California. Keeping them from rising any further has become the chief focus of lawmakers and regulators in the past several years. Any proposals that could raise customer bills even more face a tough battle — including plans to build grid infrastructure for electric truck-charging hubs.

SB 410 does give the CPUC permission to allow utilities to increase their spending in order to meet tighter EV-charger energization timelines. But the bill also calls on regulators to subject these requests to​“extremely strict accounting.”

PG&E was the first utility to submit a ratemaking mechanism under SB 410 earlier this year. The Utility Reform Network, a ratepayer advocacy group, quickly filed comments protesting the utility’s plan to create a ​“balancing account” that would enable it to recover as much as $4 billion in additional energization-related spending from customers — a structure that falls outside the standard three-year ​“rate case” process for California utilities.

“PG&E’s electric rates and bills are now so high that they threaten both access to the essential energy services that PG&E provides and the achievement of the state’s decarbonization goals, which rely in part on customers choosing to electrify buildings and vehicles,” TURN wrote in its comments.

TURN wants the CPUC to limit the scope of SB 410’s extra cost-recovery provisions to ​“specific work needed to complete an individual customer connection request,” rather than the kind of proactive upstream grid investments that truck-charging advocates are calling for. TURN would prefer that those projects remain part of general rate cases, the sprawling proceedings that determine how much utilities spend on their grids.

But those general rate cases can take up to five years to move from identifying the broader, systemwide analyses of how much electricity demand is set to rise to winning regulatory approval in order to build the expensive grid infrastructure needed to actually meet those growing needs. That’s too long to wait to fix the problem, charging advocates say.

At the same time, ratepayer advocates are challenging utility efforts to expand the scope of their larger-scale plans to meet looming EV charging needs. In SCE’s current general rate case, TURN and the CPUC’s Public Advocates Office, which is tasked with protecting consumers, are protesting that the utility is overestimating how much money it needs to spend to prepare its grid from growing EV-charging needs.

Terawatt and other charging developers and electric truck manufacturers argue just the opposite — that the utility isn’t planning to spend enough over the next three years. In his testimony in the rate case, Terawatt’s Berry complained that TURN and PAO are challenging utility and state forecasts of future charging needs based on outdated data, and that failing to approve the utility’s funding request will ​“ensure that California fails to achieve its zero-emission vehicle goals.”

Charging advocates have also asked the CPUC to create a separate regulatory process to consider the grid buildout needs spurred by large-scale charging projects. But the CPUC rejected that concept in its decision last week, stating that ​“preferential treatment based on project type is prohibited by California law.”

All these conflicting imperatives leave the CPUC with tough choices to resolve the gap between charging needs and grid buildout plans, said Cole Jermyn, an attorney at the Environmental Defense Fund.

The CPUC ​“can and should do more here. I don’t think the timelines they set here are as strong as they could have been,” Jermyn said.

At the same time, ​“the commission had an incredibly difficult job here. The targets are not easy to set, and they had a very short timeline to do it.”

That’s why multiple groups have asked the CPUC to focus its next phase of work on implementing SB 410 and AB 50 on a key issue: aligning grid planning and EV charging needs.

“Part of the work here is figuring out what that proactive planning looks like,” Jermyn said. ​“The utility cannot wait around for customers to come to them and say, ​‘We need 5 megawatts of capacity.’ They need to be looking out into the future to start proactively preparing their distribution grids for all this electrification.”

At the same time, ​“how do you balance that need for proactive planning and investment with ratepayer investments along the way to make sure this isn’t building assets that won’t be used and end up on someone’s bills?” Jermyn asked. That will be complicated, but, he added, ​“I think it’s doable — especially for a state that has such clear goals.”

SB 410 also specifically called on the CPUC to take California’s decarbonization goals into account in tackling energization delays — but last week’s decision ​“was relatively silent on that issue,” Jermyn said.

“This is something we think is incredibly important to be in the next phase of this proceeding, because it wasn’t in this one,” he said. ​“We don’t know if the timelines they set are meeting that goal or not. We should figure out if they are.”

EDF has advocated for years for utilities and regulators to approve grid spending in advance of EV charging needs, noting that such spending will end up reducing costs for utility customers in the long run.

That’s because California’s utilities don’t earn profits directly through electricity sales. Instead, their rates are structured to repay their costs of doing business. More customers buying more electricity can spread out the costs of collecting the money that utilities need to operate and invest in infrastructure, which can reduce the rates per kilowatt-hour that utilities must collect in future years.

This isn’t just a California issue. Nearly a dozen states — including Massachusetts, New Jersey, New York, Oregon, Vermont, and Washington — have adopted advanced clean truck rules. They’re not as aggressive as California’s rules, but meeting them will still require grappling with the same challenges around proactive grid planning.

Voltera’s Ashley worried that the CPUC’s decision may set a bad precedent for other state regulators on this front. ​“The commission has a really hard job. They’re tasked with a lot of complicated policy and execution,” he said. ​“And at the end of the day, they have some overarching mandates, including affordability for ratepayers,” that complicate the task.

But California also has ​“the most aggressive targets, goals, and statutory requirements around not just electrification of transportation but electrification of other segments” of the economy, he said. ​“If California doesn’t get this right, who will?”

Source: Energynews.us

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post California’s backlogged grid is holding up its electric truck dreams appeared first on Energy News Beat.

 

Austria Loves Russia Gas

Energy News Beat

Daily Standup Top Stories

Is driving electric now more expensive than petrol or diesel?

Britain’s public charging network is facing criticism for high costs, making electric vehicle (EV) driving potentially twice as expensive as using petrol or diesel cars. The UK now has over 12,500 rapid and ultra-rapid charging […]

Austria election brings into focus Russian gas addiction

  The government that takes power in Austria after next Sunday’s (29 September) general election will face growing pressure to diversify its energy supply away from dependence on Russian gas, just as the economy is […]

Highlights of the Podcast

00:00 – Intro

00:56 – Is driving electric now more expensive than petrol or diesel?

03:05 – Austria election brings into focus Russian gas addiction

06:26 – California sues Exxon over global plastic pollution

10:29 – Market Updates

14:03 – Outro

Follow Stuart On LinkedIn and Twitter

Follow Michael On LinkedIn and Twitter

ENB Top News

Energy Dashboard

ENB Podcast

ENB Substack

ENB Trading Desk

Oil & Gas Investing In 2024

– Get in Contact With The Show –

Video Transcription edited for grammar. We disavow any errors unless they make us look better or smarter.

Michael Tanner: [00:00:10] What’s going on, everybody? Welcome into the Tuesday, September 24th, 2024, edition of the Daily Energy News. Beat Stand up. Here are today’s top headlines. First up, is driving electric now more expensive than petrol or diesel? This is a great little article out of the UK. We’ll stay abroad. Austria election brings into focus Russian gas addiction. Ooh, crazy. Then we’ll come back to our favorite state. California Sues Exxon over Global Plastic Pollution. Unbelievable. I will then quickly finish off and talk all things oil and gas finance guys, as always. I am Michael Tanner. Stu is out on assignment, so I am rocking a solo show [00:00:56][45.8]

Michael Tanner: [00:00:56] So let’s go ahead and kick it off. First up here is driving electric now more expensive than petrol or diesel? This is actually a study that came out of England. Britain’s public charging network is I’m going to read straight from the article here is facing criticisms for high costs, making the EV driving potentially twice as expensive as using petrol or diesel cars on a year over year basis. UK has actually added about 12 2500 rapid and quote unquote ultra rapid charging stations, which is about a 40% increase year over year, according to some data that was shared with the Times. These chargers cost an average of 80 pounds per kilowatt hour, which makes it extremely difficult for people who don’t have access to a low cost home charging network to actually make the switch. So just like in the United States, where we spend all of this money to build out infrastructure that nobody uses. They build out all this rapid charging infrastructure. And now guess what? You can’t use it because it’s so expensive. What’s even funnier is, according to that same report, even those using the slower public chargers may pay more per mile than petrol or diesel. [00:02:07][71.0]

Michael Tanner: [00:02:07] I mean, guys, here’s the thing. The reason why gasoline and fossil fuels are currently dominating the market is because they’re so efficient. It’s the lowest cost, most efficient fuel. It’s not just the lowest cost. It’s not just the most efficient. It’s lowest cost combined with the most efficient. That’s what everybody looks for. So the market will gravitate towards things that work. People in the UK want to use EVs. They’d love nothing more. We know. We know how they are up here in the UK. I’m sorry if anybody’s listening to this from the UK, but we you know, you guys, these are definitely a little bit more left leaning than us here in the States. So we know you want to use EVs. The problem is you can’t because there are unfortunately too expensive or they do take too much time. I love to call Ultra rapid. It’s like, shit, takes what, 20 minutes to charge? So they’re dying over in the UK due to these EVs. And again, I think you’re going to, you know, something that you and I have talked about. I think you’re going to see people continue to move between hybrids, which gives you a little bit of best of both worlds. [00:03:05][57.3]

Michael Tanner: [00:03:05] Let’s move on to the next one. Austria election brings into focus a Russian gas addiction. This one’s interesting. So they have an election coming up here on September 29th. And one of the biggest I would say, issues right now in this election is where they’re getting their gas. This general election and I’ll read straight from the article, is facing growing pressure on both sides of the political aisle to diversify its energy supply away from its dependance on Russian gas. Just as the economy is stuck in reverse gear. I’ll continue on here. No party is expected to win enough seats to win an outright majority. Opinion polls give a slim lead to the opposition far right Russian friendly Freedom Party. And the result could influence the speed of a so-called energy transition. Here’s a quote from Stefan Schmemann. Buchan is a senior economist for the Australian Institute of Economic Research. Other countries aren’t happy. Austria is still consuming such large volumes of Russian gas. If you guys remember, the EU committed to phasing out Russian gas by 2027 after the invasion of the Ukraine. But you know, even with that pledge, 83% of Austrian gas was still being imported via Russia. To give a comparison to the rest of the EU, only 15% of gas imported was from Russia. So it’s pretty unbelievable. They they’re saying, hey, we want the low, we want the lowest cost energy. I mean, they need it. Opinion polls do show that FPO support at around 27 to 29%, which it’s lead slipping to as little as one point over OVP, with three parties forecasted to win close to 10% or more. The FPO, which is that conservative leaning party, says that Russia, quote, Russian gas must remain part of Austrian energy mix. And they say there’s another little quote here. Okay, here we go. Chancellor Karl Nehme Heimer, he’s The Australian’s People Party, has pledged to win the quarter of Russian gas. The high dependance on Russian gas supplies is a major economic security risk for Austria. Hey, I mean, you’re probably right from that standpoint. The ministry said in a statement, is therefore essential for our country to seek further reduce gas consumption and stop buying Russian gas. Well, the question is, okay, where are they going to diversify from? They noted that there’s much more Norway gas that they could take, which would be a great boon for Norway. Clearly, they’re going to continue to start drilling up that North Sea. So it goes to tell you, having diversification is great. You never want to be blending on one on on one person or one import for your oil. I mean, China imports from anywhere. India imports from everywhere. You always want to make sure you are not you don’t have a choke point or you’re dependent on one person. So again, do I think they should wean themselves off Russian gas? I don’t know. You should have multiple people. You shouldn’t have 85% of your gas from one country, whether it’s Russian or not. You probably should need to wean that down a little bit. The problem is some analysis from the former utility head of regulator E Control, Walter Bolts says that a 20 or a sudden stop to Russian supplies would likely book a wholesale gas price by about 20% for 2 to 6 months. So that’s a decent amount. If you’re middle to lower income Austrian, that’s a significant if for six months, that’s a prolonged period. They’re obviously dealing with inflation. So Austria is in a upper creek without a pattern is going to be interesting to see what happened. The election. We will be closely following it. [00:06:25][200.1]

Michael Tanner: [00:06:26] Let’s move on to the next one, though. California sues Exxon over global plastic pollution. This one’s pretty unbelievable, folks. So California and several environmental groups sued ExxonMobil on Monday and accused the oil giant of engaging in a decades long campaign that helped fuel plastic waste pollution. California Attorney General Rob Bonta, who spoke at an event, guess what? Climate Week in New York City, said that the state sued Exxon after concluding a nearly two year long investigation where he says that Exxon has been deliberately misleading the public about the limitations of recycling. This all specifically centers around Exxon’s promotion of what they were calling, quote unquote, advanced recycling, which is a process called Pro Lois’s. I don’t know, guys. I’m not an English major here. All I know is that this process turns hard to recycle plastics into fuel. He said that this technology, slow progress, is a sign of Exxon’s ongoing deception. Unbelievable. The technology, slow progress is a sign of Exxon’s ongoing deception. Well, maybe it’s a hard problem to solve. Has this dude ever gotten out of his little comfy ag office to figure that out, or is he too busy hobnobbing on his private jet that he flew over to New York City to talk it, quote unquote, Climate Week, where they have the A.C. cranked up and are probably using Russian gas to do that. I mean, it’s just dripping in irony. All of this. Here’s the quote from our good friend Bonta AG over there. Today’s lawsuit shows the fullest picture to date of ExxonMobil’s decades long deception. Well, I thought it was just a two year long deception over this advanced fuels thing. But we’ll get to that. And we are asking the court to uphold Exxon’s fully accountable for its role in actively creating and exacerbating the plastic pollution crisis to its campaign of deception. Here’s here’s Exxon’s response. It’s a good one, actually. Suing people makes headlines, but solving the plastic waste problem won’t advance. Recycling is a real solution. Has an addict adding that California has done nothing to advance cause like which is true. They’ve done nothing to do that. So this again, is political retribution because this is not like ExxonMobil. And I mean, this does Exxon even have facilities in California? I know Chevron does. It just it just boggles my mind that with all the craziness going on in California, everything that’s going on, the craziness that’s going on in California, this dude assigned his staff to try to sue ExxonMobil. And guess what? Newsflash, you ain’t going to win because Exxon is going to have just a few more resources than you have to fight this. And again, you’re you can’t win here. You can’t win here. Exxon, if they don’t care about recycling and just continue to produce oil, well, they’re going to you know, they’ll hit them on the climate change front. But if they actually try to do something, this advanced plastics problem, which I it’s hard. I mean, recycling stuff because newsflash and I’m pointing at the camera, you guys don’t separate your recycling properly enough if you the listener, actually separated your recycling better, Maybe this stuff works, but you don’t. Okay, so what? So they’re trying. Well, maybe there’s some hard to recycle stuff. Or maybe there’s a mixture. Let’s figure out a way to actually recycle it. Then they get burned for that because it’s a quote unquote, deceptive process. It’s unbelievable. It’s why you should in my opinion, if I was running it, I wouldn’t even worry about. Sure, let them sue us. It’s a write off that we get. Well, we’ll hire some lawyers there. I mean, there’s other stuff going on. I mean, we know the stuff that’s going on in West Texas in there fundamentally, and their fundamental disregard for the ability to plug old wells. I mean, they should be focused on that stuff, which is actually harming the environment versus this, we’re actually trying to do that. I mean, it’s unbelievable. This stuff gets me worked up, you know, I guess environment. You know, you’re going to read this article. Environmental groups Praise the lawsuit. Oceans plastic campaign directors in California’s lawsuit will hold the industry accountable and debunk the plastic recycling narrative that holds us back from real solutions. You know what? I want to debunk your Oceana stuff. That’s Kristy. That’s what I want to do. So just just unbelievable. [00:10:29][242.7]

Michael Tanner: [00:10:29] I’m going to move on before I get to worked up. Let’s move into finance, guys. Before we do that, as always, we got to pay the bills. Thank you for checking us out on the world’s greatest website. www.energynewsbeat.com. The best place for all your energy, oil and gas news. Stu and the team do a tremendous job making sure that website stays up to speed. Everything you need to know to be the tip of the spear when it comes to the energy and the oil and gas business. Go ahead and hit the description below for all the links, the types of links to the articles, and check us out on substack The energy news be a substack.com and you can also check us out and invest in oil dot energy news beat if you are interested in on our exclusive direct working interest project that we are really excited to be partnering with the team over at Pecos Country operating again that’s invest in oil dot energy news be.com. [00:11:12][42.6]

Michael Tanner: [00:11:13] Pretty wild day for the oil markets and it will start overall the S&P 500 up about 2/10 of a percentage point. Nasdaq up about three quarters of a percentage point excuse me, 3/10 of a percentage point. Man, really off there. A two year yields down a half a percentage point. Ten year yields Absolutely. Flat dollar index basically flat, maybe up a 10th of a percentage point. Bitcoin was down about a quarter of a percentage point, but still $62,145. Crude oil after a wild swing was up on the overnight trading session to about 7165 spiked briefly up to about 170 or about 7171. It then took an absolute tumble all the way down to 69, 65. But as we record this here at about 230 here on the 23rd, it stands at about 7045, such down about three quarters of a percentage point. Brant Oil is actually up three, a quarter of a percentage point day over day. Natural gas up eight percentage points after. Again, we’ll get to kind of why natural gas is up for that reason. And then we did see the actual PE contract, which is our EMP stocks, our basket of EMP stocks. It was basically flat up about 0.05 percentage points. I mean, oil and gas prices really swinging mainly due to the fact that there’s a new hurricane that looks horrible, that sweeping through the Gulf. Most of the production will end up being shut down. So I think some of that price action, what you’re seeing specifically on the natural gas is due to that, but $2.60 gas. I mean, if that if there’s something more to this, which again, it’s a lot of the storm worries. So I don’t want to say, this is a movement to the upside. We are hopefully moving into the winter season where maybe we see a little bit shift in gas prices. So but we will see what happens after this hurricane. We hope everybody and our and our oilfield workers out there in the Gulf of Mexico stay safe. We really we really hope that it was interesting to see we did see euro business activity, quote unquote, contract sharply and unexpectedly this month in which was kind of not picked up on by the street. We did see. Here’s Dennis Keisler, senior vice president of Trading Bulk Financial. Disappointing economic numbers blowing from China along with a surprise slowdown in European manufacturing is placing crude demand at its lowest levels so far this year. Not not good supply. Concerns also stemming from the ongoing Israeli airstrikes on Hezbollah has also helped support oil prices. I mean, it could be continuing to go crazy here in terms of what could happen. We also did hear on on on Monday from Chicago Fed President Austan Goolsbee or Goolsbee, whatever his name is, quote unquote. He said many more rate cuts over the next year as banks central bank seek a soft landing for the economy. So and you can see it up on my backside there on CNBC. So it looks like there are things happening there. So who knows? Folks, I don’t want to come out and say, look, it’s ready. It’s not ready. But right there, you know, we could see a lot more rate cuts, which could be interesting. [00:14:02][168.9]

Michael Tanner: [00:14:03] That’s really all I’ve got, though. Everything else on on on oil was was pretty flat. Pretty, pretty chill. There were some interesting Twitter stuff going on. You know, it looks like there’s rumors of a gearing up for a specific some M&A action. So we will be covering all that and a bag of chips as it comes through, guys. But with that, I’m going to let you get out of here, get back to work. Start your day. Sure. Will be rocking a solo show tomorrow. I will be back in the chair for the Thursday show to help wrap this whole thing up, guys. So I will see you Thursday. Say, say hi to you tomorrow. We’ll see you then. [00:14:03][0.0][828.5]

– Get in Contact With The Show –

The post Austria Loves Russia Gas appeared first on Energy News Beat.

 

U.S. LNG Permit Freeze Sparks Export Boom in Canada and Mexico

Energy News Beat
The Biden administration’s pause on new LNG export permits has created a market opportunity for Canada, Mexico, and Argentina to increase their LNG exports to Asia.
These countries are investing billions of dollars in LNG export infrastructure, particularly on their Pacific coasts, to gain a logistical advantage over U.S. exporters.
The increased LNG exports from these countries could help Asian buyers reduce their reliance on coal and achieve their climate goals, but the U.S. may lose market share in the long term.

Canada and Mexico are rushing to fill the natural gas vacuum left by the United States’ ongoing moratorium on new liquefied natural gas (LNG) export permits introduced by the Biden Administration in January of this year. The country’s neighbors to the north and south are speeding up their own export capacities to the tune of tens of billions of dollars to capitalize on the newfound market opportunity to provide natural gas to Asian buyers as the world’s biggest LNG exporter takes a break.

On January 26th, President Biden announced that it would pause approvals of new licenses to export LNG so that the U.S. Department of Energy could take time to review and assess whether the nation’s considerable LNG exports are “undermining domestic energy security, raising consumer costs and damaging the environment.”

Canada, for its part, wasted no time at all rushing to fill the sizeable gap left by the United States. According to figures from Rystad Energy AS, Mexico and Canada have around  US$63 billion of capital investment lined up to supercharge their respective LNG export capacities. “(Customers) want alternative suppliers,” Kenny Stein, vice president of policy at the Institute for Energy Research, recently told the Financial Times. “They are happy to have more supply on the market from non-U.S. suppliers.”

From a climate perspective, increasing LNG exports from Canada and Mexico are an extremely welcome addition to global markets, particularly for Asian buyers – although they alone will not be able to provide the volumes of LNG needed to wean Asia off of coal. “Massive volumes of coal must be displaced through the 2030s and beyond across emerging Asia to achieve the region’s net-zero aspirations. This inevitably will mean substantial gas imports,” Nikkei Asia reported earlier this year. “As the sole realistic coal alternative in terms of affordability and energy density, LNG from the U.S. offers a much cleaner option for always-available power generation that, in partnership with renewables, can meet growing energy demand while facilitating climate progress,” the report continues.

Despite their relatively smaller export capacities, Canada and Mexico could have critical strategic advantages over U.S. suppliers that allow them to export LNG to Asian markets more efficiently. The two countries are planning to significantly build out their LNG export infrastructure on their Pacific coasts, allowing them to avoid transporting LNG through the Panama Canal. This could give Canada and Mexico a key edge in LNG markets, as the Canal has become a global choke point for LNG trade in recent years. Exporting directly from the West Coast “would give [Canada and Mexico] easier and potentially cheaper access to the Asian markets that are forecast by the industry to drive growth,” according to reporting from the Financial Times.

And Canada and Mexico are not alone in the rush to capitalize on Asian buyer’s demand for new sources of LNG. A floating natural gas project off the coast of Argentina could soon emerge as a new supplier for Eastern markets as BP’s Pan American Energy seeks to negotiate contracts with Asian consumers. Pan American is just one of a number of companies aiming to turn Argentina into a major player in global oil and gas markets. Notably, YPF, Petronas, and Tecpetrol are all working on major projects in South America, which sits atop the world’s second-largest shale gas reserves. At present, Argentina is one of just four countries producing shale gas at a commercial scale, alongside the U.S., Canada, and China.

This means that when the United States ends its permitting freeze, the marketplace will be significantly changed. LNG exporters should brace for a much higher level of competition from LNG exporters across the Americas who may have key logistical advantages over U.S.-based enterprises.

By Haley Zaremba for Oilprice.com 

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post U.S. LNG Permit Freeze Sparks Export Boom in Canada and Mexico appeared first on Energy News Beat.

 

Oil Price Slide Eases as Tropical Cyclone Looms over Gulf of Mexico

Energy News Beat

Shell, Chevron, and Norway’s Equinor have all begun evacuating staff from offshore facilities as the threat of a potential Tropical Cyclone System 9 intensifies as it moves toward the Gulf coast, where the brewing storm could turn into a hurricane by Wednesday.

Earlier on Monday, Chevron completed the evacuation of nonessential personnel from the Gulf of Mexico facilities, including Anchor, Big Foot, Blind Faith, Jack, Petronius, and Tahiti platforms.

Shell said on Sunday that it was monitoring the storm track for potential impact on its assets and operations in the Gulf of Mexico, and was preparing to shut in production at two platforms–Stones and Appomattox. Shell has also evacuated non-essential personnel from its Mars Corridor assets as a precautionary measure.

Equinor has evacuated non-essential staff from its Titan platform.

Tropical Storm and Hurricane Watches have been issued for Cuba and parts of Mexico, with the National Hurricane Center (NHC) warning that the tropical cyclone system, which was near western Cuba on Monday, is expected to intensify over the next 72 hours.

As of noon on Wednesday (ET), the NHC said there was a 90% chance this storm would develop over the next two days, with a Harris County meteorologist stating that it will likely escalate into a Category 4 hurricane as it moves across the GoM’s warmer waters.

Oil prices on Monday were responding more to European economic data than to the potential disruption of oil supply from the Gulf of Mexico or intensifying conflict developments in the Middle East.

At 4:13 p.m. ET on Monday, Brent crude was trading down 0.59% at $74.05, while the U.S. crude benchmark, WTI, was trading down 0.47% at $70.53.

By Tom Kool for Oilprice.com

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post Oil Price Slide Eases as Tropical Cyclone Looms over Gulf of Mexico appeared first on Energy News Beat.

 

Energy Dependency: Europe’s Achilles Heel?

Energy News Beat
Mario Draghi’s report highlights Europe’s declining competitiveness, attributing it to lagging productivity, energy dependency, and an investment gap.
Draghi proposes a three-pronged solution: a more assertive industrial policy, increased public and private investment, and regulatory reforms for greater flexibility and efficiency.
The report emphasizes the need to address Europe’s energy challenges through renewable energy, infrastructure investment, and market reform, while also acknowledging unanswered questions about the cost of social welfare and talent attraction.

Mario Draghi’s much-anticipated report on European competitiveness, released on September 9th, provides a comprehensive assessment of Europe’s economic challenges and proposes solutions.

The report has garnered mixed reactions, with some praising its thoroughness and others criticizing its recommendations.

Draghi’s Assessment of the European Economy

Draghi highlights the decline of the European economy, evidenced by a falling share of global GDP and trade.

He attributes this primarily to lagging productivity, particularly in digitalization. This has led to a significant gap in disposable income growth compared to the U.S.

The report points out the disappearance of the foundations on which European prosperity was built, including energy security and sources of growth.

The continent faces challenges such as a protectionist global environment, Chinese subsidized manufacturing, and tech domination.

Draghi also criticizes Europe’s fragmented response to these challenges, particularly in climate policy.

He argues that the Green Deal’s focus on energy transition without job and industry creation has led to deindustrialization.

The report identifies energy dependency, an investment gap, and excessive regulation as further obstacles to European competitiveness.

Draghi’s Three Main Solutions

Industrial policy: The report advocates for a more assertive industrial policy, taking inspiration from China. Draghi proposes categorizing industries and sectors based on strategic importance and implementing corresponding courses of action, including accepting imports for lost industries, promoting domestic production for strategic industries, developing joint ventures, and protecting infant industries. 
Tackling the investment and innovation gap: Draghi calls for a massive increase in public and private investment, estimated at €750 to €800 billion annually. He recommends completing the Capital Markets Union and Banking Union and advocates for direct public investment through common debt for EU projects. 
Reforming the EU for flexibility and efficiency: Draghi suggests removing excessive bureaucracy and damaging legislation, particularly those based on the precautionary principle. He proposes impact assessments for law packages and evaluating policies after implementation. The report also calls for increased EU efficiency through political centralization, including extending qualified majority voting.

Energy Challenges and Solutions

A key focus of the report is Europe’s energy dependency, which Draghi sees as undermining its economic model.

The reliance on imported natural gas, particularly from Russia, has resulted in high electricity prices, putting pressure on businesses, especially energy-intensive industries like chemicals and metallurgy. This has created a significant competitive disadvantage for European companies compared to their US counterparts.

The report also criticizes Europe’s fragmented response to the energy crisis and the challenges of climate policy.

He argues that the Green Deal’s focus on energy transition without sufficient consideration for job and industry creation has led to deindustrialization.

To address the energy challenges, Draghi proposes a multifaceted approach:

Promoting renewable energy and energy efficiency: The report emphasizes the need to accelerate the transition to renewable energy sources and improve energy efficiency across all sectors.
Investing in energy infrastructure: Draghi calls for significant investments in upgrading energy infrastructure, including modernizing electricity grids and developing interconnections to facilitate the integration of renewable energy.
Reforming the EU energy market: The report advocates for a more integrated and efficient European energy market, reducing fragmentation and promoting competition.

Unanswered Questions and Contradictions

While the Draghi report offers valuable insights and solutions, it leaves some important questions unanswered.

The feasibility of debt-driven EU funding and the accountability for productive investments remain concerns.

The report also avoids addressing the cost of Europe’s social model and its impact on investment and competitiveness.

It’s also missing some clear answers on how to attract and retain top talent while maintaining Europe’s egalitarian values.

What’s Next? 

Mario Draghi’s report serves as a wake-up call for Europe, highlighting the urgent need for reform and investment.

It proposes a more assertive industrial policy, increased public investment, and regulatory reforms to address the challenges facing the European economy.

But the report’s silence on the cost of the European social model and the complexities of attracting top talent leaves some crucial questions unanswered.

The future of European competitiveness hinges on addressing these challenges and striking a balance between social welfare and economic dynamism.

By Michael Kern for Oilprice.com

Take the Survey at https://survey.energynewsbeat.com/

1031 Exchange E-Book

Crude Oil, LNG, Jet Fuel price quote

ENB Top News 
ENB
Energy Dashboard
ENB Podcast
ENB Substack

The post Energy Dependency: Europe’s Achilles Heel? appeared first on Energy News Beat.